Office moves are won or lost in the two months before moving day. After 25 years of moves, this is the checklist that keeps day one productive — phones ringing, systems reachable, nobody sitting in a beautiful new office with no internet.
60–90 days out: circuits and contracts
- Order circuits first. Internet is the longest-lead item. Get quotes for the new address (fiber DIA primary + a different-network backup — see our redundancy guide).
- Check your existing contract. Moving often triggers termination fees or renewal traps. Note your term end date; moves are your best renegotiation moment (see contract negotiation).
- Confirm phone system portability. Cloud VoIP moves with you (update E911 address!). On-prem PBX moves cost $3–10k in vendor labor — often the trigger to finally switch to hosted (see hosted PBX).
30–60 days out: design and order
- New floor plan: network drops per desk, WiFi ap locations, phone positions, conference rooms, printer locations.
- Order network gear (switches, APs, firewall) — 2–4 week lead times typical.
- Schedule low-voltage cabling contractor for the moment construction finishes.
- Inventory what moves vs what dies: old phones, aging switches, that UPS from 2016. Replace during the move, not after.
- Confirm elevator/alarm/fire lines at the new building — many must stay POTS or move to compliant POTS replacement.
2 weeks out: pre-stage everything
- Rack and configure the new network in the old office. Test firewall rules, VLANs, WiFi, VPN.
- Pre-provision every phone with the new system config; label per desk.
- File porting paperwork for any number changes; schedule cutover windows — the number porting guide maps the 2–4 week timeline.
- Book movers for the server/IT room separately from furniture crews.
Moving weekend: cutover
- Friday evening: power down, pack, move, rack, power up in order: firewall → core switch → APs → phones.
- Verify in this order: internet, internal DHCP/DNS, WiFi, one test call, all ring groups, door access, alarms.
- Update the E911 address with your VoIP provider. Seriously — this one saves lives and takes four minutes.
Week one: the list everyone forgets
- Update address with ALL vendors (including your old landlord’s forwarding for any stray mail-in payments).
- Test inbound from outside (cell), outbound, fax, and the front-door buzzer.
- Walk the floor with the first 20 users’ issues — fix patterns, not tickets.
- Decommission the old circuit only after a full business week of stable new service. Then confirm the old contract actually cancelled in writing.
Most moves are the right moment to re-platform everything — you’re touching every desk anyway. If you’d rather have an advisor run the telecom side of the move (circuits, quotes, porting, cutover), that’s free.